December 2014 Course Conditions
Course Conditions
All three courses are doing well and we’re progressing well
on the playability items for 2014-2015. (See below)
Playability Items for
2014/2015
In the November Course Conditions report we identified the
items that we are starting to work on in preparation for the new budget cycle
in Jan. 2015. The items marked with highlighted blue font have been completed per the Nov. schedule. We are making very
good progress even with a couple of rain days and having to cover greens twice.
Legacy Hills
Legacy Hills
Greenside Bunkers
*** The greenside bunkers will
start to be shelled out the week of 11/17/14. We will play all greenside
bunkers as ground under repair until
the project is complete. We look to have this completed before the end of the
first quarter of 2015.
A majority of the staff’s time has been spent working on
the bunkers and we have completed emptying #7 and #10 greenside bunkers.
*** All tree bids will be obtained in December so that they
will be valid for a January start time.
HOLE #1
•
Recommend this hole become a "cart
path only" hole
full-time.
•
Place native rocks along cart path near green
area. Will get rock from native
12/8/14 Area is prepared for rock
HOLE #3
*** Start Date Week of 12/08/14
•
Create a DG area under the trees on the right
side of the fairway, between the bunkers and the cart path. $1300
Started prep work week of 12/8/14
•
Create a DG area under the trees at the right
front of the green. $300
HOLE #8
•
Large tree on the left side needs trimmed to
remove fairway overhang. $1400
HOLE #9
•
Eliminate two of the 4 exits and repair the
remaining 2; make hole "cart path only"
until the repair is healed. $1600
HOLE #12
•
Trim the trees on the right side of the left
blue tee box. $1000
•
Install a DG approach to the green tee box. $300
HOLE #14
•
Trim the trees on the left side of all tee boxes
in Berry Creek. $5,000
Trimmed trees that we were able to reach
week of 11/24/14
White Wing
HOLE #2
Remove and replace DG at the blue
tee area. Add DG $800
11/17/14 – Added DG to level off curb drop off and raked clean
(finished)
- Place river rocks at the curb between the blue and green tee. Use Rock from #6
11/18-19/14 – Brought over rock from bed on #6 to level off this
drop off. Swept in DG and dirt to fill gaps (finished)
- HOLE #5
- GREEN TEE: Remove and replace the damaged steps; rework entire tee box and re sod with Zoysia turf. $13,000 Waiting on Bid
- HOLE #6
- Replace damaged tee monument. $800
- Remove rock walkway and replace with mulch with a rock border. To be used on #2
11/18-19/14 – Removed rock walkway and relined bed border with
rock, will add mulch after Jan 1 and finish then
- HOLE #7
- Place river rocks along the cart path between #7 green and #8 tee box.
12/9-10/14 Added rocks and dirt to correct this drop off (finish
this week)
- HOLE #8
- Major tree trimming needed from the tee area to the green. $10,000
- HOLE #14
- Major tree trimming on the right side from tee to green. $5000
- HOLE #17
- Flower bed left of green and behind the sales center, must be reworked. $400
We
estimate another $10,000 in approach drainage
work can be done on holes #14, #15 and #16.
Cowan Creek
HOLE #1
•
Suggest possible DG area under the group of trees on the
right side of the fairway. $800 (11/4/14 – limbed up trees, began clearing out underbrush)
(12/9/14 – almost finished prepping area. Need to hand dig around exposed native rock, then add decomposed granite, then define the border)
(12/9/14 – almost finished prepping area. Need to hand dig around exposed native rock, then add decomposed granite, then define the border)
- HOLE #3
- Recommend installing more French drains on the left side of the fairway. $1000 (late December – early January)
- HOLE #5
•
Continue to improve the drainage issue near blue tee area to
prevent DG from washing away with each rain. $500 (January 2015)
- HOLE #6
•
Improve the drainage on the left side of the fairway. $1000 (11/10/14 – exposed drainage pipe on the left side near
landing area, began unclogging drain from daylight and flushing sediment
buildup)
(12/9/14 – finished removing crushed and root-filled pipe, waiting on pipe and fittings delivery. Still need to install new pipe, re-grade lower drainage area, cut down large willow tree in native)
(12/9/14 – finished removing crushed and root-filled pipe, waiting on pipe and fittings delivery. Still need to install new pipe, re-grade lower drainage area, cut down large willow tree in native)
- HOLE #16
•
Expand the DG area at the blue tee box. $600 (late November)
(12/8/14 – finished adding decomposed granite to expanded area. Complete.)
(12/8/14 – finished adding decomposed granite to expanded area. Complete.)
- HOLE #18
•
(Safety issue) Place more large rocks adjacent to the
cart path in the creek area to minimize the severe drop off. $800 (late November)
(11/20/14 – complete)
(11/20/14 – complete)
Greens Covering
Per the Greens Covering policy we have had to cover twice in
2014.
Soil Testing
We have sent December’s disease samples in and are awaiting
the results from the lab.
Moisture Monitoring
Here is an example of one week’s worth of moisture
monitoring from Cowan Creek. The moisture meter we use in the field is the Fieldscout TDR 300. I have one
available for demonstration after the meeting concludes for those interested in
seeing how it works.
We received the "feature sets" of our irrigation
maps from the original irrigation design company. All three maps have been printed out using a
plotter from the CA so they are large enough to be edited (adding wildlife
areas). Once the wildlife areas are added to the maps, they will be transferred
back to a .pdf file for submittal. This
will take a few weeks for completion. We
continue to update our pesticide record spreadsheets from this year, and will
move onto our case studies for each course after the site maps and pesticide
records are completed.
White Wing #1 Green
On November 24th we were able to locate the
drainpipe that provides the drainage for #1 green at WW. As you can see the
pipe was crushed and has been preventing the proper flow of drainage from this
green.
During this time we also lowered the front collar of the
green to take out the “sand dam” that was preventing surface drainage. We have
the area marked as ground under repair and have stopped using the front half of
this green for pin placements until we have improved health of that
section.
GCSAA Certification
Attended the USGA webinar on preparing putting
greens for winter stress.
Attended Floratine University (fertilizer
seminar)