The weather slowed things down a bit but here is the current status of the greenside bunkers at Cowan Creek.
The back nine greenside
bunkers have been renovated and filled with new sand. Holes #1 and #2
have been shelled, but still need liner and sand to be complete. Holes #3
and #4 have the new liner, and are in the process of being filled with sand.
Holes #5, 7-9 are finished as well. All of the bunkers will need sod near
the lip of the bunker, but the contractors are waiting for every bunker to be
complete before ordering and laying the sod.